A sprint retrospective is the team's regular chance to look back at the sprint and decide what to change. Done well, it's the meeting that makes every other meeting better. Done badly, it's an hour of the same three people repeating last sprint's complaints. This guide walks through a simple four-step agenda that works for new and experienced teams alike.
What a retrospective is for
The goal isn't to list everything that happened. It's to find one or two things worth changing, and to agree who will change them. Everything in the agenda below serves that goal: collect honest input, see the patterns, pick what matters most, and turn it into action.
Before you start, set the scene in a minute or two:
- Remind everyone of the sprint. The sprint goal, what shipped, anything unusual such as an incident or a holiday.
- Check last retro's action items. Were they done? If not, why not? (More on this in retro action items that actually get done.)
- Agree the ground rule. We're here to improve how we work, not to blame people.
Step 1: Creating, write privately
Give everyone five to ten minutes to write their thoughts on cards, on their own and in silence. A classic set of prompts is: what went well, what didn't, what should we start doing, and what should we stop doing.
Writing privately matters more than it looks. When people call out ideas one by one, the first answer anchors everyone else, and quieter people agree instead of adding their own view. Silent writing gets you more ideas and more honest ones.
In Votenir, cards stay hidden while people write, and an eye-slash icon marks your own cards as visible only to you. When the writing slows down, the Scrum Master reveals the cards one by one or all at once.
Step 2: Grouping, find the themes
Once the cards are visible, read them out and cluster cards that say the same thing. "Deploys took forever" and "QA environment kept going down" might both belong to a group called "Release process". Give each group a short name.
Grouping does two jobs. It turns twenty separate cards into four or five topics you can actually discuss, and it shows how many people noticed the same problem. Keep it quick: if two people disagree about where a card belongs, either place is fine.
On a Votenir board you drag a card onto another to group them, then rename the group inline. Adding new cards is closed from this phase on, so the board stays stable while you sort it.
Step 3: Voting, pick what matters
You won't have time to discuss every group, so let the team choose. Each person votes for the themes they most want to talk about. A small, fixed number of votes forces real choices.
In Votenir, each member has one vote per group and can take it back. A live "Done Voting" counter shows who has finished, and when everyone is done the board moves on to Discussing by itself.
Step 4: Discussing, agree action items
Start with the group that got the most votes and work down. For each one, spend a few minutes on why it happened before jumping to what to do. Then write down a concrete action item and give it one owner.
Stop when the timebox runs out, even if some groups are left. Two action items the team will actually do beat ten that nobody remembers next week.
Votenir orders the groups by votes in this phase, so the biggest themes come first. Action items go into the Action column with an owner each, and you tick them off as Done when they're finished.
A 60-minute agenda
| Part | Time | Output |
|---|---|---|
| Set the scene | 5 min | Everyone remembers the sprint and last retro's actions |
| Creating | 10 min | Cards written privately |
| Grouping | 10 min | Four or five named themes |
| Voting | 5 min | Themes ranked by the team |
| Discussing | 25 min | One to three action items, each with an owner |
| Close | 5 min | A quick check on how the retro itself went |
Shorter sprints need shorter retros. For a one-week sprint, 30 to 45 minutes is usually enough.
Tips for the facilitator
- Keep the phases separate. Writing, grouping, voting and discussing each need a different kind of thinking. Mixing them is how retros overrun.
- Take the temperature. A quick anonymous mood check (Votenir's mood poll asks Very good, Good, Ok or Bad) tells you how the sprint felt before anyone speaks.
- Hand over the role now and then. A different facilitator brings a different view. In Votenir the board's owner can delegate acting Scrum Master rights to a teammate for the session.
- Celebrate the good sprints. Retros aren't only for problems. Saying what worked helps the team keep doing it.
Running a remote or hybrid team? Read running a retro with a remote or hybrid team for what changes when not everyone is in the room.
Questions
How long should a sprint retrospective be?
About 60 minutes for a two-week sprint, as in the agenda above. For a one-week sprint, 30 to 45 minutes is usually enough.
Who attends a sprint retrospective?
The whole team that worked on the sprint, plus a facilitator, usually the Scrum Master. Handing the facilitator role to someone else now and then brings a fresh view.
How often should we hold one?
At the end of every sprint, before the next one starts. Open each one by checking last retro's action items.
What if nobody speaks up?
Start with silent writing, so everyone adds their thoughts before anyone talks. In Votenir, cards stay hidden until the Scrum Master reveals them, and an anonymous mood poll shows how the sprint felt.